Features / Grading & Earthworks

Grading, site roads, and erosion control

PVX.AI grades utility-scale solar sites three ways, matched to the problem: area grading smooths a whole PV area to slope targets and can engineer the site roads in the same run, pad grading cuts a level pad under each rack, and targeted terrain adaptation moves only the ground under piles that miss their limits. Cut and fill volumes are reported on every run. On one project, PVX.AI reduced earthwork volume 70%, from 118,000 m3 to 35,000 m3, saving $727K.

Request a Demo + Free Trial

Last updated:

Three ways to grade, matched to the problem

Not every earthwork problem deserves the same earthwork. PVX.AI offers three grading paths, and picking the right one is usually the difference between moving a site’s worth of dirt and moving a rack’s worth.

Area grading reshapes a whole PV area to slope targets you set per direction, with cut/fill balance under your control, and can generate the site roads in the same run so the final surface, the volumes, and the roads are one consistent result. Pad grading cuts a real, level pad under each rack (and each BESS container) and seats it there, so the reveals and clearances the drawing reports are measured against the surface that will actually be built. Targeted terrain adaptation is the surgical option: it corrects the ground only under piles that miss their reveal or clearance limits while the rest of the site is held as constraints, which makes it the minimal-earthwork way to turn a failed constructability check into a compliant layout.

All three report cut and fill volumes, keep the original terrain as a hidden baseline, and feed the same cut/fill map, contours, exports, and Bill of Quantities.

How does grading work in PVX.AI?

One grading dialog handles all earthwork in PVX.AI, from balanced cut/fill smoothing to heavily cut-biased or fill-biased grading. It opens from the Earthworks panel on the PVX.AI ribbon and pairs method selection with slope entry in degrees, so every grading strategy runs through the same workflow. You select the boundary and set maximum threshold slopes for the North-South and East-West directions. Choose a soft or hard slope transition and click Build. PVX.AI reports total cut and fill volumes when the surface is done.

Before building, you enable the outputs you want. Keep Original Terrain retains the untouched surface so you can compare against the graded result. Show Cut/Fill Map color-codes the earthwork the build produced. Show Slope Analyzer refreshes the slope analysis table once grading completes. Because every option lives in one dialog, testing a different strategy means changing a setting and clicking Build again.

That matters because grading strategy is a design decision with a price tag. On one utility-scale project, three grading approaches were compared on the same site. The selected approach reduced earthwork volume 70%, from 118,000 m3 to 35,000 m3, and saved $727K. The comparison was practical because each candidate surface could be built and measured the same way, with cut and fill volumes reported on every run.

  • Slope limits are set per direction (N-S and E-W), matching how racks tolerate slope.
  • Keep Original Terrain preserves the pre-grading surface in a separate AutoCAD layer for before/after comparison.
  • The cut/fill map colors every mesh triangle: red for cut, green for fill, with volume and depth per triangle.

Cut/fill balance: ratio slider or fill cap

PVX.AI offers two balance methods. Expand the Cut/Fill Balance section of the grading dialog and pick one. The Cut/Fill Ratio slider runs from -1 to +1 with a live diagram that updates as you drag. Centered at zero, it balances cut and fill volumes to minimize imported or exported soil. This is the classic smoothing result: material cut from the high spots fills the low spots, and the site needs little or no soil moved in or out.

Dragging the slider biases the earthwork in either direction. A cut-biased surface produces surplus material that has to leave the site. A fill-biased surface needs imported material to make up the difference. Which way you drag depends on your haulage economics: bias toward cut when exporting soil is the cheaper problem to have, and bias toward fill when importing material costs less than hauling spoil away. The live diagram shows the balance shifting before you commit to a build.

The Max Fill Height method works from a hard constraint instead of a ratio. You cap the maximum fill height, and PVX.AI produces a cut-heavy result that keeps every fill area within the cap. Limiting fill to 1 m, for example, produces a surface that minimizes fill while staying within that constraint. Use this method when your project needs a hard ceiling on fill depth rather than a target balance.

What is pile-adapted grading?

Pile-adapted grading (Adapt to Pile) grades only beneath and around installed tables instead of regrading the whole site. The problem it solves shows up after you place tables on a 3D surface: some rows end up with insufficient panel-to-ground clearance, and on steep local slopes, pile lengths can exceed structural limits. Fixing a handful of rows should not require regrading the entire site, and with Adapt to Pile it does not.

Adapt to Pile opens from the Layout panel. You set two constraints. The first is a maximum above-ground rear pile length, with typical limits like 2.0 m or 2.5 m; the check compares above-ground pile length only. The second is a minimum front panel-to-ground clearance. Start the process and PVX.AI cuts a real, level pad under each table that needs one, seats the table on its pad, and measures the resulting reveals and clearance against that pad surface, scoped to the selected PV Area. Table tilt angles stay unchanged.

After processing, the new surface appears and a cut/fill map shows the localized grading zones. Grading is limited to the footprint width of each table row, preserving the natural terrain between rows. Toggle the original and modified terrain layers to compare the result before and after. To finish, regenerate contours from the modified surface using Create Contour under Civil Analysis.

The same targeted approach powers the fix path in Collision Analysis: racks a vertical shift cannot save hand off to terrain adaptation, which corrects the ground only under the out-of-band piles while every other rack in the area is held as a constraint. The scan then reports exactly what the fix cost in cut and fill.

Roads engineered in the same grading run

A road that only exists as plan-view geometry tells you nothing about whether a water truck can climb it. PVX.AI generates site roads as part of the grading run: enable Generate Roads in the grading dialog, pick the site entrance points, and the road alignments are routed on the graded surface using a cost model that weighs grading effort, curvature, and drainage crossings. The road corridors are then regraded back into the surface, so the final terrain, the cut/fill volumes, and the roads are one consistent result instead of three documents that disagree.

The engineering travels with the road. Design limits like maximum grade and turn radius are derived from your grading targets and site azimuth, and every value can be edited. You set the driveable width; shoulders and side slopes are added on top, so the corridor cleared on site is wider than the lane. Mass haul is accounted with a swell factor and free haul distance. Where a road must cross a drainage channel, PVX.AI sizes the culvert from the design rainfall you specify: return period, rainfall intensity, and runoff coefficient. No design rainfall, no invented pipe diameter.

Generated roads respect road-rack setbacks, get corner rounding at every junction, and stay connected across rack-free ground. Devices placed later align to the road that serves them, and cable trenches can follow the generated roads.

Erosion control that survives review

Stormwater review does not ask whether you drew silt fence. It asks why the basin is the size it is. PVX.AI computes RUSLE soil loss for the site and places sized erosion-control structures: check dams, sediment basins, diversion swales, and silt fences, using a storm, soil, and cover-management model with inputs you control.

You set the design storm return period, check dam height, minimum contributing area for basins, and the sizing criterion, either SCS Curve Number runoff volume or the EPA static rule. The RUSLE factors (rainfall erosivity, soil erodibility, cover management, support practice) default to values fetched from global datasets for the site location and stay overridable when your geotech report says otherwise. Subcatchment delineation is one checkbox.

The output is a soil-loss screening map plus placed, sized structures with a defensible basis, which is what turns an erosion plan from a drawing into an argument. The same erosion model feeds the culvert sizing in road generation, so the drainage story is consistent across the site.

Earthworks outputs

After grading, you regenerate contours from the modified surface with one command and export earthworks data as CSV. The Earthworks export pairs the pre-grading and post-grading surfaces point by point, with five columns: Northing, Easting, NGL (natural ground level), FGL (finished ground level), and Difference, where positive is fill and negative is cut. Run it after a grading operation; an ungraded site has no paired points to export.

Contour generation is under your control. The Generate Contours dialog sets the minor interval spacing and makes every Nth contour bold and labeled, with a live preview that updates as you change the values. Generated contours land on dedicated major, minor, and label layers, replacing any existing contours there, so regenerating after each grading run keeps the drawing current.

Graded terrain also exports as PVsyst-compatible CSV. Both pre-grading and post-grading variants are available, so the surface you model in PVsyst matches the surface you plan to build.

Cut/fill volumes also flow into the Bill of Quantities civil works sheet, itemized alongside site preparation, roads, cable trenches, and earthing. The Info Screen summarizes the same volumes alongside total installed DC power, pile quantities with minimum and maximum pile lengths, and the rack slope distribution.

$727K Earthwork cost savings CS#1: 70% less earthwork volume (118K → 35K m³) across 3 grading approaches

"We adopted PVX.AI mid-project and it picked up our existing layout without losing a step. It handled grading and routing automatically and caught an excavation issue that would have been costly to fix in the field."

Hatice Elif Beyazitli Celik

Hatice Elif Beyazitli Celik

Analysis & Projecting Process Leader · EnerjiSA

Frequently asked questions

How does PVX.AI balance cut and fill volumes?

The Cut/Fill Ratio method balances cut and fill volumes when centered, minimizing soil import and export. Dragging the slider biases the result toward more cut or more fill. Alternatively, the Max Fill Height method caps fill height and produces a cut-heavy surface that respects the cap.

Can PVX.AI grade only under the tables instead of the whole site?

Yes. Adapt to Pile grades only beneath and around installed tables to satisfy minimum ground clearance and maximum pile length constraints, scoped to a selected PV Area. Terrain between rows stays natural.

Does PVX.AI keep the original terrain after grading?

Yes. The original surface is kept in a separate AutoCAD layer as a hidden baseline. Toggle layers to compare before and after, and inspect both in 3D Orbit.

What earthwork volumes does PVX.AI report?

Total cut and total fill volumes are reported after every grading run, per-triangle volumes appear on the cut/fill map, and the Bill of Quantities export itemizes earthworks under civil works.

Can I export grading results for civil contractors?

Yes. The Earthworks CSV export pairs pre-grading and post-grading surfaces point by point (NGL, FGL, difference), and graded terrain exports to PVsyst-compatible CSV in both pre-grading and post-grading variants.

Can PVX.AI design solar site access roads?

Yes. Road generation runs inside the grading pass: alignments are routed between your site entrances on the graded surface with a grading, curvature, and drainage-crossing cost model, then the road corridors are regraded into the final terrain. Culverts are sized from your design rainfall, and mass haul is accounted with swell factor and free haul distance.

Does PVX.AI handle erosion control for solar farms?

Yes. It computes RUSLE soil loss and places sized erosion-control structures (check dams, sediment basins, diversion swales, silt fences), with SCS Curve Number or EPA static basin sizing and overridable RUSLE factors fetched from global datasets for the site location.

What is the difference between area grading, pad grading, and targeted terrain adaptation?

Area grading reshapes a whole PV area to slope targets with cut/fill balance control. Pad grading cuts a level pad under each rack or BESS container and seats it there. Targeted terrain adaptation corrects the ground only under piles that miss their reveal or clearance limits, holding the rest of the site as constraints. All three report cut and fill volumes.